Create a rule to set drainage node to (active terrain) when setting elevation reference
Presently when setting reference elevation for the node it lets you set it to the active terrain but does not rule it to the (active terrain). If this were done the inlet tops would automatically adjust as the design terrain changes.
DU: add drop calculation to node invert depending on lowest conduit wall thickness
Some times, most common with concrete conduits, the node invert needs to have a drop in reference to the lowest pipe to acomodate its wall. This would later be filled to match.For construction and BIM purpose, this difference is important. Special...
Add profiles from different horizontals to a rollplot sheet
Would like an easier way to add multiple profiles to a single sheet that belong to different horizontal alignments. Specifically we're looking for a way to quickly place all the drainage profiles (which below to different horizontal alignments) on...
Export multiple terrain models as a single XML file
We deliver terrain models for top/bottom surfaces of a roadway. Due to gaps in project data we often have multiple top surfaces and multiple bottom surfaces. It would be nice to export all surfaces as a single XML file similar to alignments.
Cross section view should show Point name of a template drop
when using the point control function. It is expected to see the names of points of a template drop in the cross section view. This would be utilized when using the point control function.
currently creating complex geometry is irreversible and extremely difficult to edit. neither on-screen nor table edit work well to modify complex geometry, especially removal of PI with curve sets. Also, delete element from complex is not unattain...
Ability to have multiple superstructure types in one bridge definition. For example, steel main spans with concrete approach spans is currently defined as 3 bridges
Many bridges have approach spans that are smaller in length to the main spans. For example, a bridge that crosses over a railroad ROW may have prestressed concrete in the approach spans and a continuous steel bridge over the railroad, then the end...
Separate 3D line and 3D object for pipes to different levels.
In Drainage & Utilities, the 3D line and the 3D object for a pipes(conduit/link) is placed on same level. It would be great to have them on different levels - also because it can be a demand from from clients in Denmark, that the line is place...